Make Ready (Last Planner System)

It is essential that the latest planners work each week from the current 6 week preparation plans. For project teams to document and advance their phase plans, a common concern is the amount of work that the update requires each week to produce a 6 week readiness plan. Here are a few tips. (3 weeks, 6 weeks, 12 weeks, 20 weeks) Before work starts, team leaders make tasks ready so that when work should be done, it can be. Why put work into production if a pre-requisite is missing? This MakeReadyprocess continues throughout the project. (process validation plan, process purchasing, process contract,...) process validation plan, process purchasing, process contract
  • LUDOVIC GARCIA
  • Feb 23 2018
  • Shipped
  • Attach files
  • Guest commented
    July 30, 2018 12:50

    It is critical for me, as a CM to be able to see, extract and print if needed at least a months look ahead rather than seeing weeks activities on the screen

    Thanks

  • Mario Samson commented
    July 30, 2018 12:08

    An existing customer has asked for this exact topic today again.

  • Admin
    David Jung commented
    February 27, 2018 10:09

    Hi Ludovic,

    glad you are using our ideas portal!

    If I understand your idea correctly, you would like to put an information into the system which marks activities as ready to be started, right?

    If so, could that not be translated into "all predecessor activities done" which is an information we already have on Sablono?

    Or are there cases were all predecessor works have been ticked as completed but still the team is not able to start on the following activities for a certain reason? Which reasons might that be?


    Best,
    David